A step-by-step guide to planning, controlling, monitoring and analysing budgets in Klirr: from creating a budget and getting it approved, through changes after approval and actuals, to forecasts, risks, findings and reports. Every step shows the real screen, who may do it, the exact permissions and what changes afterwards.

Versjon
2.0.1
Oppdatert
Kapitler
13
leksjoner
63

Kapittel F

Monitoring and analysis

Dashboard, budget vs actual, availability and drill-downs, variance and consumption reports, certification.

Step 17

Executive dashboard #

What
See the company's budget position for a fiscal year.
Where
Menu › Budget Intelligence › Executive Dashboard
Who
Budget Manager, Finance Manager, Accountant, Auditor, Company Administrator, Business Owner
Permission
  • klirr.client.budget-intelligence.read
Figures follow per-budget View grants on restricted budgets.
Prerequisites
At least one Approved budget that has been calculated.

How

The numbers match the numbered markers on the screenshot.

  1. Choose scope: Company, Project or Budget.
  2. Choose the Fiscal year.
  3. Read the warning box first.
  4. Check Calculation, Last calculated, Certification, Data coverage.
  5. Approved / Released / Actual / Open commitment.
  6. Available.
  7. Forecast at completion.

Field guidance

  • All figures come from one server read — nothing is computed in the browser.
  • Formulas: see chapter H (KPI reference).

Why

One place to judge whether spending, commitments and forecast are within plan, and how reliable the figures are.

Expected result

Demo company FY2026: Approved 86,427,500.00; Actual 57,590,438.19; Open commitment 2,400.00; Available 28,834,661.81; Utilisation 66.64 %.

Impact

  • Read-only.

Dependencies

  • Last nightly or manual calculation; posted journals; commitments.

Common errors and recovery

  • "Data coverage is low" → many lines have no matching actuals yet (see Troubleshooting).
  • "Provisional, not certified" → see Year-end certification.

Next:Step 18 · Budget › Budget vs actual tab

Step 18

Budget › Budget vs actual tab #

What
Compare each account's budget with posted actuals.
Where
Budget › Budget vs actual tab
Who
Budget Manager, Finance Manager, Accountant, Auditor, Company Administrator, Business Owner
Permission
  • klirr.client.budget-intelligence.read(menu)
  • klirr.client.accounting.management-accounting.read(budget pages)
A restricted budget also needs a View grant.
Prerequisites
Budget Approved or Closed.

How

The numbers match the numbered markers on the screenshot.

  1. Open the tab.
  2. Header tiles: Original, Revised, Actual, Variance.
  3. Budget per account (revised amounts).
  4. Actual from posted journals.
  5. Variance = Actual − Budget.
  6. Variance % = Variance ÷ Budget × 100.

Field guidance

  • Actual here covers the whole fiscal year (also postings dated after today).
  • Unbudgeted activity (below the table): actual on the budget's accounts under a dimension combination no line has — not in the totals.
  • Negative variance = below budget for both revenue and cost lines; red does not mean "bad".

Why

The quickest way to see which accounts are under or over plan.

Expected result

Demo BDGT-008: 3000 Sales budget 53,127,400.00, actual 39,451,967.40, variance −13,675,432.60 (−25.74 %).

Impact

  • Read-only.

Dependencies

  • Posted journal lines matching account and dimensions exactly.

Common errors and recovery

  • Actual differs from the Availability tab → different date basis (see chapter H, "Why two Actual figures").
  • Variance % blank → budget is 0.

Next:Step 19 · Budget › Availability tab

Step 19

Budget › Availability tab #

What
See what is still available per line after actuals and commitments.
Where
Budget › Availability tab
Who
Budget Manager, Finance Manager, Accountant, Auditor, Company Administrator, Business Owner
Permission
  • klirr.client.budget-intelligence.read(menu)
  • klirr.client.accounting.management-accounting.read(budget pages)
A restricted budget also needs a View grant.
Prerequisites
Budget Approved or Closed.

How

The numbers match the numbered markers on the screenshot.

  1. Recalculate / Run Budget Intelligence (Step 16).
  2. Freshness line.
  3. Formula note.
  4. Click Actual to see the journal lines behind it.
  5. Click Open commitment to see its sources.
  6. Available.
  7. Headroom against plan.
  8. Commitments / Movements per line.

Field guidance

  • Available = Released − Actual − Open commitment (what may still be committed).
  • Headroom against plan = Revised − Actual − Open commitment (a planning figure).
  • Window = the line's period, cut at today ("as of").
  • Checks = control warnings on the line.

Why

Availability is what budget control checks when someone raises a purchase request, order, supplier invoice or expense.

Expected result

Demo 3000 Jan: Released 2,605,800.00 − Actual 1,458,436.85 − 0.00 = Available 1,147,363.15.

Impact

  • Read-only; drill-downs open side panels.

Dependencies

  • Movements, commitments, posted journals.

Common errors and recovery

  • A drill-down "Does not reconcile" → report to the administrator with the line and date.

Next:Step 20 · Drill-down: journal lines behind Actual

Step 20

Drill-down: journal lines behind Actual #

What
Prove an Actual figure from the posted journal lines.
Where
Budget › Availability › click an Actual amount
Who
Budget Manager, Finance Manager, Accountant, Auditor, Company Administrator, Business Owner
Permission
  • klirr.client.budget-intelligence.read(menu)
  • klirr.client.accounting.management-accounting.read(budget pages)
A restricted budget also needs a View grant.
Prerequisites
Approved budget with postings.

How

The numbers match the numbered markers on the screenshot.

  1. Total of all rows vs Figure on screen.
  2. Status "Reconciles" confirms both are equal.
  3. Each row: document, date, description, status.
  4. Account and amount in base currency.

Field guidance

  • Rows are journal lines with status Posted or Reversed (a reversal and its original net to zero).
  • Only lines whose account and dimensions match the budget line exactly, dated within the line's window up to today.

Why

Every figure can be traced to its source documents.

Expected result

Demo 3000 Jan 2026: 1,458,436.85 NOK, Reconciles.

Impact

  • Read-only.

Dependencies

  • General ledger postings.

Common errors and recovery

  • Expected document missing → check its posting date, status (draft documents are not actual) and dimensions.

Next:Step 21 · Drill-down: sources of the open commitment

Step 21

Drill-down: sources of the open commitment #

What
See which documents commit budget that is not yet spent.
Where
Budget › Availability › click an Open commitment amount
Who
Budget Manager, Finance Manager, Accountant, Auditor, Company Administrator, Business Owner
Permission
  • klirr.client.budget-intelligence.read(menu)
  • klirr.client.accounting.management-accounting.read(budget pages)
A restricted budget also needs a View grant.
Prerequisites
Approved budget with open commitments.

How

The numbers match the numbered markers on the screenshot.

  1. Total of all rows.
  2. Reconciles.
  3. Source document (SB = supplier bill, PO/PR = order/request).
  4. Status of the source document.
  5. Amount in base currency.

Field guidance

  • Demo: SB-00000055 "Office cleaning, monthly", status PendingApproval, 2,400.00 on 40 Cost of goods sold.

Why

Commitments reserve budget before the cost is posted, so availability is not overstated.

Expected result

Demo 40 Oct 2026: open commitment 2,400.00, Reconciles.

Impact

  • When the bill is posted, the commitment ends and the amount becomes Actual.

Dependencies

  • Supplier bills, purchase requests and orders (see chapter E).

Common errors and recovery

  • Bill without exchange rate is left out and the line is flagged incomplete.

Next:Step 22 · Budget variance page

Step 22

Budget variance page #

What
Compare budget and actual for one budget or all budgets of a year.
Where
Menu › Budget Intelligence › Budget variance
Who
Budget Manager, Finance Manager, Accountant, Auditor, Company Administrator, Business Owner
Permission
  • klirr.client.budget-intelligence.read(menu)
  • klirr.client.accounting.management-accounting.read(budget pages)
A restricted budget also needs a View grant.
Prerequisites
Approved or Closed budgets.

How

The numbers match the numbered markers on the screenshot.

  1. Budget (empty = all budgets of the year).
  2. Fiscal year.
  3. Cost centre / profit centre filters.
  4. Chart or table view.
  5. Original budget.
  6. Variance (Actual − Revised).
  7. Unbudgeted actual.

Field guidance

  • With no budget chosen, a key shared by several budgets has its budgets added and its actual counted once.
  • Only Approved or Closed budgets are reported.

Why

Company-wide view for management reporting, filterable by cost and profit centre.

Expected result

Demo FY2026 (BDGT-008 + BDGT-009): Original 86,401,000.00; Revised 86,402,500.00; Actual 58,107,687.91; Variance −28,294,812.09.

Impact

  • Read-only.

Dependencies

  • Posted journals for the whole fiscal year.

Common errors and recovery

  • "This budget is not Approved or Closed, so it has no variance report." → approve it first.

Next:Step 23 · Budget consumption page

Step 23

Budget consumption page #

What
Track budget, actual, remaining and consumption % by month.
Where
Menu › Budget Intelligence › Budget consumption
Who
Budget Manager, Finance Manager, Accountant, Auditor, Company Administrator, Business Owner
Permission
  • klirr.client.budget-intelligence.read(menu)
  • klirr.client.accounting.management-accounting.read(budget pages)
A restricted budget also needs a View grant.
Prerequisites
Approved or Closed budgets.

How

The numbers match the numbered markers on the screenshot.

  1. Budget filter (only Approved/Closed offered).
  2. Chart or table view.
  3. Remaining = Budget − Actual.
  4. Consumption % = Actual ÷ Budget.
  5. Read each period row.

Field guidance

  • Budget per period uses revised plan amounts (movements such as supplements are not included).
  • Whole-year lines are never prorated: they appear as "Unscheduled budget".

Why

Shows the pace of spending through the year.

Expected result

Demo BDGT-009: Nov budget 84,500.00 (60,000 + 9,500 + 12,000 + 3,000); Dec 53,000.00; actual 0.00.

Impact

  • Read-only.

Dependencies

  • Period lines; posted journals.

Common errors and recovery

  • All months flat → the budget has only whole-year lines; phase them (Step 5).

Next:Step 24 · Year-end & close › Certification

Step 24

Year-end & close › Certification #

What
Check whether the position can be certified and why not.
Where
Budget › Year-end & close tab
Who
Budget Manager, Finance Manager, Accountant, Auditor, Company Administrator, Business Owner
Permission
  • klirr.client.budget-intelligence.read(menu)
  • klirr.client.accounting.management-accounting.read(budget pages)
A restricted budget also needs a View grant.
Prerequisites
Budget calculated at least once.

How

The numbers match the numbered markers on the screenshot.

  1. Certification status (Certified / Provisional / Not certified).
  2. Reasons it is not certified.
  3. Ledger total vs Attributed to lines.
  4. Unattributed amount.
  5. Show reconciliation per account.
  6. Year-end carryforward (company setting).

Field guidance

  • Ledger total = Attributed to lines + Unattributed; Difference should be 0.00.
  • Demo BDGT-008: 64,212,273.19 = 57,590,438.19 + 6,621,835.00 → Provisional ("Ledger activity on budgeted accounts matches no budget line, above the tolerance").

Why

Certification tells you whether the forecast and position rest on complete data.

Expected result

You know whether to trust the forecast and which accounts block certification.

Impact

  • Dashboard shows "certified" / "not certified" on the forecast tile.

Dependencies

  • Dimensions on postings; budget lines covering all posted combinations.

Common errors and recovery

  • Provisional because of unattributed actual → add a line for the combination or correct the postings' dimensions.

Next:Executive dashboard: chart, requests and risks

Executive dashboard: chart, requests and risks #

  1. Budget requests: waiting and by status (demo: 2 Applied).
  2. Open risks: count and total exposure across budgets.
  3. Severity counts and top risks (links to the budget's risks).
  4. Budgets in scope with Last calculated.
  5. Certification and data coverage per budget.

Total exposure adds every risk's potential exposure; several rules can flag the same money, so the total (102.7 M NOK) can exceed the budget (86.4 M NOK). Use it to rank, not to sum.

Executive dashboard: position by fiscal month #

  1. Legend: Actual in month, Open commitment (columns); Released, Available, Forecast (cumulative lines).
  2. Columns: actual posted in each month.
  3. Released (cumulative): flat at the approved envelope.
  4. Forecast (cumulative) rises towards the forecast at completion; Available falls as actual grows.
  5. Show as table gives the exact monthly values.

Axis values are raw amounts (100000000.00 = 100 M NOK). Lower on the page: Multi-year trend (budget vs actual per year), Capex / Opex split and Risk ranking by cost centre — these come from a transitional read and use plan figures.