A step-by-step guide to planning, controlling, monitoring and analysing budgets in Klirr: from creating a budget and getting it approved, through changes after approval and actuals, to forecasts, risks, findings and reports. Every step shows the real screen, who may do it, the exact permissions and what changes afterwards.
Spending ahead of schedule (UtilizationAheadOfSchedule)
Utilisation % − elapsed % of period
≥ 30 pts High, ≥ 15 pts Medium
Commitments use up what is left (CommitmentsConsumeRemaining)
Commitment ÷ (available + commitment)
≥ 90 % Critical, ≥ 70 % High
Budget nearly used up early (BudgetNearlyExhaustedEarly)
Utilisation ≥ 90 % with < 60 % elapsed
Critical at ≥ 100 %
Spend off the phased plan (VarianceFromPhasedBudget)
Deviation from revised × elapsed share
≥ 40 % High, ≥ 20 % Medium
Sharp forecast movement (MaterialPeriodMovement)
Forecast change between runs
≥ 30 % High, ≥ 15 % Medium
One supplier dominates commitments (SupplierConcentration)
One supplier ≥ 50 % of commitments
Medium
Source data is out of date (StaleIntegrationData)
Integration data older than 48 h / 144 h
Medium / High
Missing cost or profit centre (MissingDimensions)
Spend ≥ 5,000 without dimensions
Low
Too little data to trust (IncompleteDataCoverage)
Line's data coverage Low
Medium
Spend booked outside this line (UnattributedSpend)
Actual on the account with another combination
Medium
Earlier recommendation still open / Material manual forecast override
Unresolved prior finding / large manual override
Medium / Low
Low data coverage caps any risk at Medium and marks it provisional. Rules treat revenue lines like cost lines: more revenue than planned is flagged as "ahead of schedule" or "forecast exceeds budget".
Risks; findings (one per open risk episode); confidence score caps; budget control decisions.
Calculations / statistics
Forecast at completion (commitment-driven, run-rate or phased), utilisation, variance, data coverage, confidence score (weighted evidence 0.30, reconciliation 0.30, cause 0.20, source 0.15, model 0.05).
Fixed playbook text (no AI)
Automatic analysis / Investigate budget: "Calculated from the recorded figures by a fixed playbook — no AI." Possible causes are labelled inferences to verify.
LLM (Rody), optional
"Ask Rody" / "Investigate with Rody" — off unless the company enables it; uses typed tools only, evidence re-verified; results labelled Rody. Not enabled for the demo budgets in this verification.
None of these change a budget, posting or approval by themselves; every action stays with a person who has the permission.