A step-by-step guide to planning, controlling, monitoring and analysing budgets in Klirr: from creating a budget and getting it approved, through changes after approval and actuals, to forecasts, risks, findings and reports. Every step shows the real screen, who may do it, the exact permissions and what changes afterwards.

Versjon
2.0.1
Oppdatert
Kapitler
13
leksjoner
63

Kapittel H

Reports and KPI reference

Exact formulas as implemented, sources, date basis, sign conventions and worked examples from the demo company.

KPIs on budget pages and variance reports #

KPI (where)Formula as implementedSource / basisWorked example (demo)Read it as
Original budget (budget header, Variance page)Σ line OriginalAmount, frozen at approvalPlan linesBDGT-009: 166,000.00The approved plan
Revised budgetΣ (Revised ?? Original)Approved revision versionsBDGT-009: 167,500.00 (+1,500)Current plan; excludes supplements
Actual (header, Budget vs actual, Variance page)Σ posted/reversed journal lines, whole fiscal yearGL, normal-balance sign, base currencyBDGT-008: 58,107,687.91Includes postings dated after today
VarianceActual − Budget (revised)Same3000 Sales: 39,451,967.40 − 53,127,400.00 = −13,675,432.60Negative = below budget (good for cost, bad for revenue)
Variance %Variance ÷ Budget × 100, 2 decimals; blank when Budget = 0Same−13,675,432.60 ÷ 53,127,400 = −25.74 %Size of the gap
Unbudgeted actualActual on budgeted accounts with a combination no line hasGLBDGT-008: 40 COGS · CC-ADM 6,621,835.00Missing line or wrong dimension
Consumption % (Consumption page)Actual ÷ Budget per period; Remaining = Budget − ActualRevised plan per periodBDGT-009 Nov: 0 ÷ 84,500 = 0.00 %Pace of spending

KPIs on availability and the dashboard #

KPI (where)Formula as implementedSource / basisWorked example (demo)Read it as
Approved (BI)Original approval + supplements + revision adj. + carry-forward − returnsMovement ledgerBDGT-009: 192,500.00Spendable envelope
ReleasedApproved + transfers in − out + additional release (Approved is released)Movement ledger7140 Nov: 12,000 + 2,000 = 14,000.00What may be used
Open commitmentBills not posted + PR/PO remaining + holds + reservationsPurchasing, controlCompany: 2,400.00 (SB-00000055)Committed, not yet posted
AvailableReleased − Actual − Open commitmentLive, cut at todayCompany: 86,427,500 − 57,590,438.19 − 2,400 = 28,834,661.81May still be committed
Headroom against planRevised − Actual − Open commitmentLive3000 Jan: 2,605,800 − 1,458,436.85 = 1,147,363.15Planning room, not spendable
Utilisation (dashboard)(Actual + Open commitment) ÷ Approved × 100Live(57,590,438.19 + 2,400) ÷ 86,427,500 = 66.64 %Share of envelope used
Forecast at completionPer line: commitment-driven, run-rate or phased (see notes)Last calculationCompany: 69,539,304.06 (not certified)Expected year-end
Forecast variance (dashboard)Forecast at completion − Approved; positive = overrunLast calculation + live69,539,304.06 − 86,427,500 = −16,888,195.94Projected under/overrun

Forecast at completion and data coverage #

Strategy (chosen per line, in this order)Used whenForecast at completion
Commitment-drivenOpen commitment ≥ 20 % of the revised lineActual + Commitment
Current run-rateActual > 0 and ≥ 8 % of the period elapsedmax(Actual ÷ elapsed share, Actual + Commitment)
Phased budgetOtherwisemax(Revised, Actual + Commitment)
  • Elapsed share uses calendar days of the line's window up to the as-of date.
  • Data coverage (Low / Medium / High) follows the strategy and the evidence; project lines whose window starts before 30/08/2026 are always Low.
  • Certification: Certified when the ledger on budgeted accounts is fully attributed to lines within tolerance; otherwise Provisional or Not certified. The dashboard then labels the forecast "not certified".
  • Worked example BDGT-009 (no actuals yet): every line uses the phased strategy, so forecast = revised plan = 167,500.00; the company forecast rises from 69,371,804.06 to 69,539,304.06 (+167,500).
  • Note: the forecast is measured against the plan (Revised), while the dashboard variance subtracts Approved — after a supplement the two bases differ (BDGT-009: 167,500 vs 192,500).

Why two different Actual figures? #

ScreenActual (BDGT-008)Date basis
Budget header, Budget vs actual tab, Budget variance page58,107,687.91All postings of fiscal year 2026, including those dated after today
Availability tab, Executive dashboard, Year-end certification57,590,438.19Postings up to the as-of date (27/10/2026) inside each line's window
Difference517,249.72Account 3000: 514,581.90 (sales invoices dated 29–31/10, posted 24/10). Account 40: 2,667.82 (an expense dated 30/10).
  • Both figures are correct for their purpose: the reports show the whole year, availability shows what has happened by today.
  • All other accounts agree to the øre (verified per account on 27/10/2026).
  • If the gap is unexpected, look for postings with a future posting date.

Signs, colours and units #

SituationCost line (e.g. 6300 Rent)Revenue line (e.g. 3000 Sales)
Actual below budgetVariance negative — favourable (saving)Variance negative — unfavourable (less sales)
Actual above budgetVariance positive — unfavourable (overspend)Variance positive — favourable (more sales)
Red figure on screenKlirr colours every negative variance redSame — red does not mean "bad" here
Forecast variance (dashboard)Positive = projected overrunPositive = more revenue than plan (rules still flag it)
  • Amounts: company accounting currency (NOK), 2 decimals, thousands separator ",". Percentages: 2 decimals.
  • A zero budget gives an empty Variance % (budget pages) or 0 % (dashboard consumption).
  • Times: UTC, format dd/MM/yyyy HH:mm (Discount budgets shows M/d/yy).